The Project is planned to start construction as early as Q3-2021. The Project will be underpinned by a [5]-year MOPU Lease Contract for MAC Field Development (“MOPU Lease Contract”) with the Husky CNOOC Madura Limited (“HCML”)
Construction
CONVERSION
TOPSIDE MODIFICATION
HULL MODIFICATION
REACTIVATION
O&M
OPERATION
MAINTENANCE
PRE-COMMISSIONING
HOOK-UP & COMMISIONING
TRANSPORTATION
INSTALLATION
EPCI
ENGINEERING
PROCUREMENT
CONSTRUCTION
CONVERSION
INTERFACE & INTEGRATION
![](https://www.ptdutamarine.co.id/storage/2021/12/Untitled.png)
![](https://www.ptdutamarine.co.id/storage/2021/12/PW8-clg-1024x819.png)
Overview
A MOPU will be built by converting [a jack-up rig] in an Indonesian shipyard. The MOPU will be operated in Indonesian waters to support the MAC oil and gas fields in the Madura Strait. The MAC oil and gas field/block are part of production sharing contract (“PSC”) between HCML with Indonesia government through the SKK Migas.
Husky-CNOOC Madura Limited (HCML) is developing MAC field gas reserves in the Madura Strait Block for sales gas to buyers in Java Island. This field is located offshore in the Madura Strait East Java, about 120 km east of Surabaya and about 25 km South East of Madura Island.
The development plan of MAC gas field involves drilling and completion of three wells at around 230 ft water depth, installation of minimum facility wellhead platform (WHP) and mobile offshore production unit (MOPU), and installation of approximately 8 km 10” export pipeline which will be subsea tied-in to existing 28″ EJGP pipeline. MAC production facilities are designed with the capacity of 60 MMSCFD to accommodate the plateau rate of 54 MMSCFD from MAC field wells that will be sustained for 5 years.
MAC WHP will be a minimum facilities 3-legs unmanned wellhead platform with 5 well slots (3 slots for present, 2 slots for future). Gas lines from each well are routed directly by using flexible jumper lines to MOPU.
Client: HUSKY CNOOC MADURA LIMITED
Location: MAC FIELD